【单选题】
A 项目团队拒绝在晚上和周末工作以完成整个产品待办事项列表 The project team refused to work evenings and weekends to complete the entire product backlog.
B 产品负责人未包括在敏捷培训中,甚至没有分配到项目中 A product owner was not included in agile training or was not even assigned to the project.
C 项目团队没有与客户协商如何确定产品待办事项列表的优先级 The project team did not consult with the customer on how to prioritize the product backlog.
D 进度基准太短,无法开发产品待办事项列表中的所有项目 The schedule baseline was too short for all the items in the product backlog to be developed.