14、The customer on a project tells the project manager he has run out of money to pay for the
project. What should the project manager do FIRST?
A、Shift more of the work to later in the schedule to allow time for the customer to get the funds
B、Enter administrative closure
C、Stop work
D、Release part of the project team
14、项目的客户告诉项目经理他已经没钱了,不能再支付该项目。项目经理应该首先做什么?
发布于 2023-03-06 16:38:39
【单选题】 A 推迟进度中的多数项目工作,以给客户时间去寻找资金 B 进入行政收尾 C 停止工作 D 解散一部分项目团队